ThermoVault
- Concept aimed at using multiple heaters to offer more than freeze protection
- Catalytic heaters sized for specific heating requirements to raise and maintain the temperature of the process fluid
- Product currently in the R&D stage
- Planned testing using a 400 bbl tank is scheduled to begin July 2010
- Energy requirements, fuel gas savings and reduction in air emissions will be compared to a conventional fire tube application for potential carbon tax credits for
producers
back to menu
Tab 2
ThermoVault Updates
August 31, 2010
- Prototype tank construction in progress and testing requirements outlined
August 4, 2010
- Multiple catalytic heaters scheduled for testing in September
June 14, 2010
- Single catalytic heater testing scheduled for the end of July
- Heater sizing calculator in development